Connect the Dots




       Dr. James Ortiz, Director
Independent Program Assessment Office
            Seventh Annual NASA
      Program Management Challenge 2010
              February 10, 2010
                                          Used with Permission
                                                        Page 1
Introduction


• The Independent Program Assessment Office (IPAO) manages
the independent review of the Agency's Programs and projects
at life-cycle milestones to ensure the highest probability of
mission success.

•This presentation provides an overview of the Agency’s policy
context for the Agency Independent Life Cycle Review process
(The “Why”, the “What”, and the “How”).




                                                                 Page 2
Outline


• Connecting the dots on the Agency policy context
   – The “Why”
       » NPD 1000.0; NPD 1000.5
   – The “What”
       » NPR 7120.5D NID; NPR 7123.1
   – The “How”
       » SRB Handbook
       » IPAO System Operating Procedures
• Summary




                                                     Page 3
Agency Policy Context for
  Independent Review




                            Page 4
Policy Flow-down


                                                                        NPD 1000.0
                                                                        NPD 1000.3
                                                                        NPD 1000.5




                              NPD 7120.4                   NPD 8700.1                     NPD 8900.5A                      Mission Support Office




                                           NPR 7120.5D                                                                                     Support Organization
         NPR 7123.1A                                                 OSMA    Directives                 OCHMO Directives
                                             and NID                                                                                             Directives


                          1        2                                     3                               4                                    5




                                                         NASA -SP 2009 -10 -015 - HQ          Center Engineering                       Mission Directorate
     NASA -SP -6105
                                                             SRB HANDBOOK                        Requirements                             Requirements
SYSTEMS ENGINEERING
      HANDBOOK
                                                                                                    7                                         6

                           IPAO 1000
                      IPAO MANAGEMENT
                              PLAN                                                        LEGEND:
                                                                                                                                                     DIRECT
                                                                                          1: ENGINEERING REQUIREMENTS
                                                                                          2: PROGRAM/PROJECT
                             IPAO 2000                                                    MANAGEMENT REQUIREMENTS
                       STANDARD OPERATING                                                                                                            INDIRECT
                                                                                          3. SAFETY AND MISSION
                            PROCEDURE                                                     ASSURANCE REQUIREMENTS
                                                                                          4. HEALTH AND MEDICAL REQTS
                                                                                          5. MSO FUNCTIONAL REQTS
                                                                                          6. MD REQUIREMENTS
                                                                                          7. CENTER REQUIREMENTS



                                                                                                                                                                Page 5
The “Why”




            Page 6
The Governance and Strategic
          Management Handbook (NPD 1000.0A)
“NASA governance and strategic management provide the discipline and rigor
to enable success of NASA’s Mission- ….
Mission success delivers on our commitment to be good stewards of the
resources entrusted to us by the taxpayer. To enable Agency-wide
accomplishments, NASA’s governance framework is founded on the following
tenets:
• …..
NASA’s governance principles that provide this framework are:
• Lean governance.
• Clear roles, responsibility and decision making.
• Strategic acquisition.
• Checks and balances. ……
There are many process-related checks and balances built into NASA’s way of
doing business. They range from peer reviews conducted at the lowest level to
oversight reviews conducted by the Agency’s Program Management Council.
Three checks and balances of particular importance at the program or project
level are: the independent life-cycle review process, the process for tailoring
a specific prescribed requirement, and the Dissenting Opinion process.”
                                                                                  Page 7
Why Independent Review
      The Governance and Strategic Management
              Handbook (NPD 1000.0A)
The independent life-cycle review process provides a comprehensive
review of programs and projects at each life-cycle milestone by competent,
independent individuals. The purpose of these reviews is to provide:

 1.   Agency wants P/p to receive independent assurance that they are on-
      track
 2.   NASA senior management wants:
       – Independent validation at key decision points of the
         Program/project’s readiness to proceed into the next phase of its
         life-cycle
       –   Externally-imposed impediments to Program/project success to
           be removed
 3.   Agency needs to give external stakeholders assurance we can deliver
      to our commitments
 4.   Significant additional benefit is that preparation for the review
      milestone allows for a holistic examination by the Program/project and
      the review team
                                                                             Page 8
Policy for NASA Acquisition
                             NPD 1000.5

• NPD 1000.5A calling for the Joint Confidence Level (JCL)
  analysis became effective in January 2009
• Policy is directed to ensure appropriate level of funding is
  provided and maintained to increase probability of success of
  the Agency’s Programs and Projects
• Requirements
   –   (a) Programs are to be baselined or rebaselined and budgeted at a confidence level
       of 70% or the level approved by the decision authority of the responsible Agency-
       level management council. For a 70% confidence level, this is the point on the joint
       cost and schedule probability distribution where there is a 70% probability that the
       project will be completed at or lower than the estimated amount and at or before the
       projected schedule. The basis for a confidence level less than 70% is to be formally
       documented.
   –   (b)           Projects are to be baselined or rebaselined and budgeted at a
       confidence level consistent with the program’s confidence level.

   –   The program's or project's proposed cost and schedule baseline are to be assessed
       by an independent review team. The program or project is to present and justify its
       resulting cost and schedule to the decision authority of the responsible Agency-level
       management council. The independent review team is to discuss with the decision
       authority its key concerns with the plans and baselines proposed by the program or
                                                                      9
       project.
                                                                                               Page 9
The “What”




             Page 10
NPR 7120.5D NID
        Independent Review Requirements

• Provides the basis for how NASA execute its space
  flight programs and projects.
• Provided a standardized life cycle review process that
  is built around Key Decision Points (KDP).
• Formalized the Technical Authority, Dissenting
  Opinion Resolution, and Waiver processes.
• Defines the Independent review policy requirements
    Standardizes the Standing Review Board concept across NASA
    Combines technical (7123) and programmatic reviews into one Board
   the Standing Review Board (SRB)
        One independent review board for each program or project
        Conducts all 7120.5-required independent reviews for that
         program or project throughout its life cycle
        Implemented by the IPAO for all Programs, Category 1 Projects
         and Category 2 projects with a life-cycle cost > 11
                                                           $250M       Page 11
Project Life Cycle   (NPR 7120.5)




                                    Page 12
Project Life Cycle   (NPR 7120.5)




                                    Page 13
NPR 7123.1 Systems Engineering
             Technical Review Requirements

•   NPR 7123.1A – Systems Engineering Processes and Requirements
        Articulates and establishes the requirements on the implementing
         organization for performing, supporting, and evaluating systems
         engineering
        This systems approach is applied to all elements of a system and all
         hierarchical levels of a system over the complete project life cycle
•   5.2.1.3      A technical review is an evaluation of the project, or
    element thereof, by a knowledgeable group for the purposes of:
        Assessing status of and progress toward accomplishing planned activities.
        Validating technical tradeoffs explored and design solutions proposed.
        Identifying technical weaknesses or marginal design and potential
         problems (risks) and recommending improvements and corrective actions.
        Making judgments on activities’ readiness for follow-on events, incl
         additional future evaluation milestones to improve likelihood of successful
         outcome.
        Making assessments and recommendations to project team, Center, and
         Agency management.
        Providing historical record that can be referenced of decisions that were
         made during these formal reviews.
•   Entrance and Success criteria for each life-cycle milestone are
    contained in Appendix G.
                                                                                       Page 14
The “How”




            Page 15
The SRB Handbook
                            The How

•   The SRB is written to provide guidance to the NASA Program and
    project (P/p) community and the Standing Review Boards (SRBs)
    regarding expectations, processes, products, timelines, and working
    interfaces with Mission Directorates, P/p, Centers, other review
    organizations, and the Management Councils.
•   The SRB handbook was published by PA&E/IPAO with concurrence
    from OCE




                                                       IR-16
                                                                          Page 16
SRB Handbook Contents


• The SRB Handbook consist of six sections
  –   Section 1: Context for Independent Lifecycle Review (ILCR) Process. Objectives,
      intent, and governance of the Standing Review Boards (SRB).
  –   Section 2: High level principles that govern the SRBs. Independence and issue
      resolution. Points to Annex with Agency policy for “Review Board Composition,
      Balance and Conflict of Interest”.
  –   Section 3: Scope and expectations of ILCR. Provides guidelines (roadmaps) for
      application of review criteria in NPR 7120.5 as a function of the lifecycle stage of P/p,
      the types of mission (Robotics versus Human Spaceflight), and type of Program (
      tightly coupled or loosely coupled).
  –   Section 4: SRB Initiation process. Roles and responsibilities for Chair/RM nomination,
      team composition and staffing, and Terms of Reference (TOR).
  –   Section 5: SRB Products. Technical and programmatic assessments, findings and
      recommendation, briefings and reports.
  –   Section 6: Notional review timeline. Describes the review phases for a typical review.
  –   Appendices: Agency Independence Policy, PIR guidance




                                                                         IR-17
                                                                                                  Page 17
Example of Section 3
                                                                                                           (SRB engagement roadmap)


NASA Life Cycle                                                          Formulation                                                                                                                            Implementation
Phases                                                           Pre-Systems Acquisition                                                                                                       Systems Acquisition                                                                             Operations
                              Pre-Phase A                                   Phase A                           Phase B                                       Phase C                                                                             Phase D                                          Phase E
Reviews                            MCR
                                           1
                                                                   SRR                   SDR                         PDR                        CDR            PRR
                                                                                                                                                                           1
                                                                                                                                                                                      SIR                      SAR               ORR               FRR
                                                                                                                                                                                                                                                              2
                                                                                                                                                                                                                                                                       LRR
                                                                                                                                                                                                                                                                                  2
                                                                                                                                                                                                                                                                                                  PFAR
                                                                                                                                                                                                                                                                                                              2


                                                                                        (PNAR)                      (NAR)
Key Decision Points                              KDP A                                                KDP B                      KDP C                                                         KDP D                                                                                  KDP E
SRB Participation             Case-by-                     Full Board             Full Board                    Full Board               Full Board       Chair and            Full Board                Chair and         Chair and          Chair and           Chair and                   Chair and
                              case                                                                                                                        Member                                         Member            Member             Member              Member                      Member
                                                                                                                                                                       3                                              3                3                  3                   3                           3
                                                                                                                                                          Subset                                         Subset            Subset             Subset              Subset                      Subset
Sample Assessments
                              Preliminary                  Functional and         Flowdown to                 Flowdown to                Any Changes,     Production           Integration               System            Phase E,           Flight              Launch                      Flight
                                                           Performance            Functional                  Functional                 Flowdown to      processes ,          Plan and                  meets             Descope            operations          system and                  performance
                                                           Baseline ;             Elements;                   Elements,                  Functional       certified            Procedures                acceptance        plans              are certified       spacecraft/                 reporting
    Requirements                                           Requirements           System                      Descope                    Elements,        design                                         criteria and                         to proceed          payloads
                                                           Traceability           Requirements                Plans                      Descope                                                         has been                                                 readiness
                                                           Report; SEMP           Document                                               Plans                                                           verified and                                             for launch
                                                                                                                                                                                                         validated
                              Key                          Preliminary            Mission                     Baseline:                  Design meets     Design               Previous                  Technical         All waivers        Hardware            Launch                      Performance
                              Technolgies,                 Approach, TRL,         System                      Systems                    performance,     documentati          component,                data              and                and                 system and                  report and
                              TRL, MOEs,                   Technology             Architecture,               Engineeering               TRL              on,                  subsystem                 package,          anomalies          software            spacecraft/                 Anomaly
                              MOPs                         Devlpt.                TRL, TDMAP,                 Mgt Plan,                                   Production           and system                Certification     have been          systems are         payloads                    resolution
                         5                                 Maturity               SEMP, SDP                   Design meets                                Plans                tests have                package           closed;            configured          readiness
         Technical
                                                           Assessment                                         performance                                                      been verified                               Operational        for flight          for launch
                                                           Plan (TDMAP),                                                                                                       to support                                  procedures
                                                           Software                                                                                                            integration                                 and
                                                           Devlpt. Plan                                                                                                                                                    contingency
                                                           (SDP)                                                                                                                                                           planning
                              ROM Cost                     ROM                    Preliminary:                Baseline:                  Performance      Production           Performance               Remaining         Performance        Performance
                              Schedule                     Integrated             BOEs        IMS             BOEs         IMS           against plans,   Plans                against                   liens or open     against            against
                              Estimates                    Cost Schedule          Cost/Budget                 Cost/Budget                EVM,                                  plans,                    items and         plans,             plans,
Integrated cost and
                         6
                                                           Estimates              UFE, CADRe                  UFE, CADRe                 UFE , LLIL                            EVM,                      plans for         EVM,               EVM,
         schedule                                                                 WBS                         JCL , Detail                                                     UFE,                      closure           UFE                UFE
                                                                                  ICE                         schedules,                                                       JCL
                                                                                                              ICE
                              Preliminary:                 Preliminary:           Preliminary:                Baseline:                  Facilities       Facilities           Facilities                Facilities        Facilities         Facilities
         Resources            Facilities                   Facilities             Facilities                  Facilities                 Workforce        Workforce            Workforce                 Workforce         Workforce          Workforce
                              Workforce                    Workforce              Workforce                   Workforce
                              Preliminary                  Preliminary            Preliminary:                Baseline:                  Risk List        Risk List            Risk List                 Risk List         Risk List          Risk List
                              Risks                        Risks                  Risk Mgt Plan               Risk Mgt Plan              Mitigation       Mitigation           Mitigation                Mitigation        Mitigation         Mitigation
             Risk
                                                                                  Risk list                   Risk list
                                                                                  Mitigation                  Mitigation
                              Preliminary:                 Preliminary:           Preliminary:                Baseline:                  Performance      Production           Performance               Performance       Phase E            Performance
     Management               Approach                     Plans                  Project Plans               Project Plans              against plans    Engineering          against plans             against           Mgt Plan           against
                                                                                                                                                          and Planning                                   Plans                                plans
Reporting Venues
           Project                    x                             x                      x                            x                         x                x                   x                          x
                         4
         Program                      x                             x                      x                            x                         x                x                   x                          x
                     4
            CMC                       x                             x                      x                            x                         x                x                   x                          x
            DPMC                      x                             x                      x
                                                                                               4
                                                                                                                        x
                                                                                                                            4
                                                                                                                                                  x                x                  x
                                                                                                                                                                                          4
                                                                                                                                                                                                                  x
            APMC                   Cat 1                                                Cat 1                       Cat 1                                                           Cat 1
Notes:
1. PRRs are only needed when multiple flight system copies are being developed; timing is discretionary.
 2. LRRs, FRRs, PFARs are performed by the Mission Management Team (MMT); the SRB Chair (and/or Designee) attend as non-voting observers.
 3. Chair determines which members should attend, including themselves.
 4. The SRB chair and RM will make themselves available to support these interim briefings.
 5. Compliance with NPR 7123.1 review entrance and success criteria will be assessed.
 6. Compliance with NPR 1000.5.                                                                                                                                                                                                       IR-18
                                                                                                                                                                                                                                                                                                                  Page 18
Example from Section 4
                                                (SRB Formulation )


                       SRB Initiation Schedule prepared monthly for the APMC
                                                                        BPR


                                                         Cat 1 &                             Cat 3 &
             Programs                              Cat 2 Projects                        Cat 2 Projects
                                                         >$250M                             <$250M


                MDAA                                       CD                                  CD
         Nominates Chair                        Nominates Chair                        Nominates Chair
                                                                                                                                       Reiterate
                                                                                                                                   selection steps
                                                                                                                                    with new Chair
              IPAO RM                                   IPAO RM                             Center RM
                                                                                                                                      nomination
           Assignment                              Assignment                              assignment

                                                                                                                                                No


                                                                                                                                 MDAA/DA/TA/PA&E*
           Nominations vettedvetted all Approval Authorities (MDAA, DA, TA, PA&E) and cleared for OCI/PCI.
               Nominations with with all Approval Authorities (MDAA, DA, TA,               PA&E)
                                                                                                                               Approval/Concurrence ?


Selection of the SRB Chair and RM
                                                                                                                                                Yes

                                                                                                                                      Reiterate as
                       Chair/RM develop                                        Chair/RM develop ToR                                  necessary to
                   SRB Membership List                                      and review with DA and TA                              obtain Approvals
                                                                                                                                                No


    Nominations vetted with all Approval Authorities                                                                             MDAA/DA/TA/PA&E*
                                                                                                                               Approval/Concurrence ?
             and cleared for OCI/PCI.

  SRB Staffing and ToR Preparation
         Participating Organizations                                                                                                   Yes
    Mission Directorate                   Host Center                                                     Proceed with SRB Reviews
           IPAO                              SRB
                                                                                              * For Programs, Cat.1 and Cat 2 (LCC>$250M) Projects only
        Joint Effort



                                                                                                                                                   IR-19
                                                                                                                                                           Page 19
Handbook Status

•   Initial version of Standing Review Board (SRB) Handbook (HB) developed
    October 2007 by Agency team (IPAO lead and representative from each
    Center).
•   SRB HB on hold pending review of Federal Advisory Committee Act (FACA)
    regulations and independence policy requirements.
•   SRB HB on hold for completion of NPR 7120.5D NID (~February 2009).
•   NID-aligned version of the SRB Handbook released for PPMB review on Sept
    25, 2009 ( 2 week review).
•   Baseline version of SRB HB published ( December 2009)
•   Next revision to be published with NPR 7120.5E




                                                             IR-20
                                                                               Page 20
IPAO

    The NASA organization responsible for the agency
          independent life cycle review process
•   Enables independent review of programs and projects to
    ensure highest probability of mission success.
•   Ensures objectivity, quality, integrity and consistency of
    independent review process per NPRs 7120.5D and 7123.1A.
         Works with SRB Chair and Convening Authorities
         Reviews SRB products to ensure they meet Agency
          expectations
•   Provides Review Manager, cost, schedule and other
    programmatic analysis SRB members
•   Provides advice and recommendations to Agency
    on program and project policies
         Book Manager for Agency’s SRB Handbook


                                                                 Page 21
IPAO Standard Operating Procedure
                 Detail processes

•   The Standard Operating Procedure (SOP) documents the Independent
    Program Assessment Office (IPAO) process for conducting
    Independent Life-Cycle Reviews (ILCRs).
•   The SOP is a guide for the IPAO personnel when conducting ILCRs of
    the Agency’s programs and projects.
•   The purpose of this document is to ensure ILCR quality and efficiency
    through the development of common definitions and processes.




                                                                            Page 22
How is it done?
                                                    (IPAO Process)
                                                          I     N    P       U     T       S
                                                                 P/p Documentation
 Agency Review             Agency/Directorate/Centers          Cost & Schedule                           SRB Briefings to           Minutes/Decisions/Actions
Schedule                    Documentation &                        Documentation                           Program/Project
 Review Chair              Requirements                         Program/Project
Nomination                                                       Briefings


      PLANNING                     PREPARING                         REVIEWING                             REPORTING                      CLOSING-OUT


      Continuous                      2- Months                       1-3 Months                             2-3 Months                         1- Month

 Monitor Agency             Initiate Contact and Determine        Receive CADRe Inputs               Verbal Pre-Briefings to P/p       Review Closeout
  Baseline Program/         Review Budget                           SRB Kick-Off Meetings              Write one-page summary            Customer
Project Review               Identify and obtain approval of       Attend Reviews                     Write the Report                    Feedback
 Determine IPAO            SRB Chair/RM/SRB members                Attend Site Visit                  Prepare the Summary               Develop Lessons
   Review Budget             Determine funding mechanism           Develop ICE/ICA/ISA                  Briefings                       Learned
 Review Assignments         Develop the TOR                                                           Present the Briefings:            Process Review
                             Develop Schedule/Logistics                                                   - Program/ project             and Improvement
                              of the Review                                                                - CMC                           Administrative
                             Develop the Cost Plan                                                        - MD PMC                       Close-out
                             Develop the Schedule Plan                                                    - APMC (if required)            Team Recognition




                                                     P    R     O      D       U       C       T   S
                                   Individual Review Budget                ICE/ICA/ISA                    One Page Summary               Review Summary
   RM/CA/SA Assignments          ToR, Cost Plan, Schedule Plan            SRB Findings                   SRB Report                     Contracts Close-out by
                                  Chair and Team Nomination                RFA                            RRD Report                    COTR
                                  and Guidance Letters                      Recommendations               SRB Briefings                   Review Records
                                   Review Schedule
                                                                                                                                            RRD Report
                                   Contract Task Statement
                                                                                                                                            Process improvements
                                   R&R for SRB




                                                                                                                                                           Page 23
SOP:Sample SRB Engagement
                            Timeline

SRB KO:                     PDR: 2/11/10   Site Visit: 5/11/10 - 5/21/10        KDP: 6/11/10 - 6/21/10
10/14/09
           PDR KO:12/1/09




                                                                           24                       Page 24
Summary


•   The independent life cycle review process is an integral part of the
    Agency’s check and balances built into the NASA governance
    structure and complements the programmatic and technical lines of
    command and authority.
•   The independent lifecycle review process is encoded as part of NASA
    policy direction; its requirements are stipulated in policy requirements;
    and guidance to reviews team and implementing personnel is provided
    in handbooks and operating procedures.
•   Its processes are continuously assessed for improvement by IPAO and
    its stakeholders.
•   The independent lifecycle review process helps ensure the highest
    probability of success of the Agency’s program and projects.