Erection
of
Steel Girder and Steel Truss Bridges
Prepared By :-
Balar Piyush 110763106063
Vekariya Sandeep R. 120763106001
Kakadiya Gaurang A. 120763106002
Balar Jigar H. 120763106003
Guided By :-
Prof. A.P. Satasia
Prof. P. V. Trivedi
Prof. R. R.Tripathi
Railway Bridge & Tunnel Engineering
† Contents
 Introduction to Steel Girder Bridges
 Erection of Steel Girder Bridges
 Methods
 Erection of Steel Truss Bridges
 References
† Introduction to Steel Bridges
 The steel girder bridge is a structure in which a floor system and roadway,
concrete or timber, is supported by girders, usually rolled section beams which
are plain or encased in concrete
 These are normally used for railways and rarely for highways
 Following data should be collected prior to the erection of these bridges:
 Time estimate for the construction of a bridge
 Condition of proper equipment and machinery
 Condition of bridge site
 Facility for transportation and storage of materials at bridge site
 Necessary supporting system for superstructure
 Availability of steel structures
 Width and depth of flow in the river
 Height of bridge from river bed
Methods for erection of steel bridges
Erection by Lifting Method
Erection by Staging
Erection by Floating
Erection by Rolling
Erection by Launching of single girder span
† ERECTION OF STEEL GIRDER BRIDGES
† Erection of Steel Bridges
 Methods
 Erection by Lifting Method
 Steel girders upto span of 30 m can be
easily erected if the height is 5 to 6 m
 This method is suitable for rivers which
are dry for the most part of the year
 A platform is created by filling earth to
sufficient height and levelled
 Girders are assembled on the river bed and field riveted/bolted
 They are lifted into position by means of stiff-leg derrick cranes or ordinary
rope worked from anchored crab winches
 The flooring and the bracings are then field connected to the girders placed in
position
SOLNA BRIDGE, STOCHOLM, SWEDEN
† Erection of Steel Bridges
 Methods
 Erection by Staging:
 Favourable conditions:
 Depth of water in the river is shallow
 Height of superstructure above the river should not be
excessive
 Span should be simply supported
 Staging consists of trestle frames which may be of steel or
timber
 Iron staging is lighter than timber staging and, therefore, can be
easily transported
 Staging is suitably designed and after it is constructed, the
erection of steel girders is commenced on the staging
† Erection of Steel Bridges
 Methods
 Erection by Floating:
 Favourable conditions for this method are:
 Depth of water in the river is more
Floating barges/pontoons are used to carry the steel girders
Bridge is assembled on the barges and is floated into position when
complete.
The barges are so positioned that
span is over the final alignment,
when the jacks are used to lower the
span on the bearings.
Finally the barges are sunk by
flooding the tanks
Coleman Bridge, York River in Yorktown
† Erection of Steel Bridges
 Methods
 Erection by Rolling:
 This method is adopted for erection of continuous girders on deep gorges
 First span near the abutment is erected by any one method of erection
 Girders of the first span are brought to the required position by rolling
them from the abutment through the erected span
 This method is also known as the Incremental Launching Method and has
become very popular for the concrete girders
 Second span is cantilevered when it projects from the erected span and
acquires counter weight for its stability
 This counter weight is provided by the successive span connected to it and
its back
† Erection of Steel Bridges
 Erection by Launching of single girder span
 Each girder is first assembled on a
track of rollers behind one of the
abutments and is cantilevered as far
as possible over the span.
 The lifting blocks are then fastened
to the outmost point of the girder
and the heavy wire is coupled to the
winch.
 Rear end of the girder is tied to
another winch which is released
slowly so that sudden forward motion
may no take place.
† Erection of Steel Truss Bridges
 These bridges are erected with the help of a stiff derrick traveller and two
false work bents
 Erection procedure may be described in four stages:
 Second stage
 Move traveller (crane) to
B
 Erect false work bent T2
 Assemble the section BC
 First stage
 Erect false work bent T1
 Assemble the section AB
† Erection of Steel Truss Bridges
 Third stage
 Move traveller to C
 Remove false work bent T1 from B
and erect it at D
 Assemble the section CD
 Fourth stage
 Move traveller (crane) to D
 Assemble the section DE
 Release the false work bent T1 and T2
† References
 ftp://ftp.mdt.mt.gov/research/LIBRARY/NSBASBEGS-1-OL-
STEEL_BRIDGE-AASHTO.PDF