When we shape the work, we need to do it at the right level of abstraction: not too vague and not too concrete. Product managers often err on one of these two extremes.
Wireframes are too concrete
When design leaders go straight to wireframes or high-fidelity mockups, they define too much detail too early. This leaves designers no room for creativity. One friend put it this way:
Iâll give a wireframe to my designer, and then Iâm saying to her: âI know youâre looking at this, but thatâs not what I want you to design. I want you to re-think it!â Itâs hard to do that when youâre giving them this concrete thing.
Over-specifying the design also leads to estimation errors. Counterintuitive as it may seem, the more specific the work is, the harder it can be to estimate. Thatâs because making the interface just so can require solving hidden complexities and implementation details that werenât visible in the mockup. When the scope isnât variable, the team canât reconsider a design decision that is turning out to cost more than itâs worth.
Words are too abstract
On the other end of the spectrum, projects that are too vague donât work either. When a project is defined in a few words, nobody knows what it means. âBuild a calendar viewâ or âadd group notificationsâ sound sensible, but what exactly do they entail? Team members donât have enough information to make trade-offs. They donât know what to include or leave out. A programmer who worked in that situation said:
Youâre solving a problem with no context. You have to be a mind reader. Itâs like: âweâll know it when we see it.â
Concerning estimation, under-specified projects naturally grow out of control because thereâs no boundary to define whatâs out of scope.
Case study: The Dot Grid Calendar
Letâs look at an example of how to shape a project at the right level of detail.
We launched version three of Basecamp without a calendar feature. It had a âscheduleâ feature that just listed events one after the other without any kind of monthly, weekly or daily grid.
Soon after launch, customers started asking us to âadd a calendarâ to Basecamp. We had built calendars before and we knew how complex they are. It can easily take six months or more to build a proper calendar.
These are the kinds of things that make a calendar complicated:
- Dragging and dropping events between cells to move them
- Wrapping multi-day events around the edge of the screen
- Different views for monthly, weekly, or daily time scales
- Dragging the edge of an event to change its duration
- Color coding events for different categories
- Handling different expectations for desktop vs. mobile interactions
Past versions of Basecamp had calendars, and only about 10% of customers used them. Thatâs why we didnât have the appetite for spending six months on a calendar. On the other hand, if we could do something to satisfy those customers who were writing us in one six week cycle, we were open to doing that.
With only six weeks to work with, we could only build about a tenth of what people think of when they say âcalendar.â The question became: which tenth?
We did some research (discussed in the next chapter) and narrowed down a use case that we wanted to solve. We eventually arrived at a promising concept inspired by calendars on phones. We could build a two-month, read-only grid view. Any day with an event would have a dot for each event. A list of events would appear below the calendar, and clicking a day with a dot would scroll the events for that day into view. We called it the Dot Grid.
The Dot Grid wasnât a full-featured calendar. We werenât going to allow dragging events between days. We werenât going to span multi-day events across the grid; weâd just repeat the dots. Thereâd be no color coding or categories for events. We were comfortable with all these trade-offs because of our understanding of the use case.
This is the level of fidelity we used to define the solution:
Rough sketch of the Dot Grid concept
Note how rough the sketch is and how many details are left out. The designer had a lot of room to interpret how this should look and feel.
At the same time, note how specific the idea is. Itâs very clear how it works, what needs to be built, whatâs in and whatâs out.
At the end of the project, the finished work that the designers and programmers created looked like this:
Screenshot of the Dot Grid when it launched
This small example highlights a few properties of shaped work.
Property 1: Itâs rough
Work in the shaping stage is rough. Everyone can tell by looking at it that itâs unfinished. They can see the open spaces where their contributions will go. Work thatâs too fine, too early commits everyone to the wrong details. Designers and programmers need room to apply their own judgement and expertise when they roll up their sleeves and discover all the real trade-offs that emerge.
Property 2: Itâs solved
Despite being rough and unfinished, shaped work has been thought through. All the main elements of the solution are there at the macro level and they connect together. The work isnât specified down to individual tasks, but the overall solution is spelled out. While surprises might still happen and icebergs could still emerge, there is clear direction showing what to do. Any open questions or rabbit holes we could see up front have been removed to reduce the projectâs risk.
Property 3: Itâs bounded
Lastly, shaped work indicates what not to do. It tells the team where to stop. Thereâs a specific appetiteâthe amount of time the team is allowed to spend on the project. Completing the project within that fixed amount of time requires limiting the scope and leaving specific things out.
Taken together, the roughness leaves room for the team to resolve all the details, while the solution and boundaries act like guard rails. They reduce risk and channel the teamâs efforts, making sure they donât build too much, wander around, or get stuck.
Who shapes
Shaping is creative and integrative. It requires combining interface ideas with technical possibilities with business priorities. To do that youâll need to either embody these skills as a generalist or collaborate with one or two other people.
Shaping is primarily design work. The shaped concept is an interaction design viewed from the userâs perspective. It defines what the feature does, how it works, and where it fits into existing flows.
You donât need to be a programmer to shape, but you need to be technically literate. You should be able to judge whatâs possible, whatâs easy and whatâs hard. Knowledge about how the system works will help you see opportunities or obstacles for implementing your idea.
Itâs also strategic work. Setting the appetite and coming up with a solution requires you to be critical about the problem. What are we trying to solve? Why does it matter? What counts as success? Which customers are affected? What is the cost of doing this instead of something else?
Shaping is a closed-door, creative process. You might be alone sketching on paper or in front of a whiteboard with a close collaborator. Thereâll be rough diagrams in front of you that nobody outside the room would be able to interpret. When working with a collaborator, you move fast, speak frankly and jump from one promising position to another. Itâs that kind of private, rough, early work.
Two tracks
You canât really schedule shaping work because, by its very nature, unshaped work is risky and unknown. For that reason we have two separate tracks: one for shaping, one for building. During any six week cycle, the teams are building work thatâs been previously shaped and the shapers are working on what the teams might potentially build in a future cycle. Work on the shaping track is kept private and not shared with the wider team until the commitment has been made to bet on it. That gives the shapers the option to put work-in-progress on the shelf or drop it when itâs not working out.
Steps to shaping
Shaping has four main steps that we will cover in the next four chapters.
- Set boundaries. First we figure out how much time the raw idea is worth and how to define the problem. This gives us the basic boundaries to shape into.
- Rough out the elements. Then comes the creative work of sketching a solution. We do this at a higher level of abstraction than wireframes in order to move fast and explore a wide enough range of possibilities. The output of this step is an idea that solves the problem within the appetite but without all the fine details worked out.
- Address risks and rabbit holes. Once we think we have a solution, we take a hard look at it to find holes or unanswered questions that could trip up the team. We amend the solution, cut things out of it, or specify details at certain tricky spots to prevent the team from getting stuck or wasting time.
- Write the pitch. Once we think weâve shaped it enough to potentially bet on, we package it with a formal write-up called a
pitch. The pitch summarizes the problem, constraints, solution, rabbit holes, and limitations. The pitch goes to thebetting tablefor consideration. If the project gets chosen, the pitch can be re-used at kick-off to explain the project to the team.